Summary of Prime Contract Mod 1262
Oct. 2, 2020
Deleted and Replaced
- Section H: Special Contract Requirements
- Clause H.53 - Paid leave under Section 3610 of the Coronavirus Aid, Relief, and Economic
Security Act (CARES Act) to maintain employees and subcontractors in a ready state
reflects a change to update the effective date range and limiting preapproval for
paid leave.
- Clause H.53 - Paid leave under Section 3610 of the Coronavirus Aid, Relief, and Economic
Security Act (CARES Act) to maintain employees and subcontractors in a ready state
reflects a change to update the effective date range and limiting preapproval for
paid leave.
- Section J: List of Documents, Exhibits, and Other Attachments*
- Attachment F, Operating and Administrative Requirements (List B), is deleted and replaced
as follows:
Prime Contract Table Action Summary Applicability Delete DOE O 350.1 Chg 6 (MinChg)
Contractor Human Resource Management Programs
Chapter VIII - Contractor Workplace Substance Abuse Programs CRD
Chapter IX - Employee Assistance Programs CRD
Approved: 09/30/96
Chg 6 (MinChg): 02/01/18CRD applicable in whole
CRD applicable in wholeAdd DOE O 350.1 Chg 7 (LtdChg)
Contractor Human Resource Management Programs
Chapter VIII - Contractor Workplace Substance Abuse Programs CRD
Chapter IX - Employee Assistance Programs CRD
Approved: 09/30/96
Chg 7 (LtdChg): 02/19/20CRD applicable in whole
CRD applicable in wholeDelete DOE O 522.1 CRD
Pricing of Departmental Materials and Services
Approved: 11/03/04CRD applicable in whole
Add DOE O 522.1A CRD
Pricing of Departmental Materials and Services
Approved: 08/02/18CRD applicable in part
Delete DOE O 551.1D Chg 2 (Minor Revision) CRD
Official Foreign Travel
Approved: 04/02/12
Chg 2 (Minor Revision): 08/09/16CRD applicable in whole
Add DOE O 550.1 Chg 1 (LtdChg) CRD
Official Travel
Approved: 05/02/19
Chg 1 (LtdChg): 12/13/19CRD applicable in whole
- Attachment J, Performance Evaluation and Measurement Plan is deleted and replaced
as follows:
Attachment J, Fiscal Year 2020 Performance Evaluation and Measurement Plan dated Sept. 23, 2020, is deleted and replaced with the Fiscal Year 2021 Performance Evaluation and Measurement Plan dated Sept. 30, 2020, and is incorporated into this contract by reference.
- Attachment F, Operating and Administrative Requirements (List B), is deleted and replaced
as follows:
Share